Llogara Tunnel, concrete lining has reached almost 2 kilometers

Albanian Deputy Prime Minister, at the same time Minister of Infrastructure and Energy, Belinda Balluku was today to see the progress of the works in the Llogora tunnel, where nearly 2 kilometers have been concreted so far. Balluku said that the tunnel is due to open to traffic in June 2024.
The works in the emergency tunnel have been progressing at a good pace and that so far about 5,000 meters have been opened, while only 400 meters remain to be opened.
“We are working on concreting lining on both sides of the tunnel, in Palasa and in Dhërmi. The tunnel has 11 emergency exits and 6 rest stops. The 5450 meter emergency tunnel is almost open, with only 400 m remaining to open. This tunnel will be completed in June 2024”, said Balluku.
The work on the construction of the Llogora tunnel with a length of 5.9 kilometers started on November 14, 2021. The tunnel starts from the bridge of Shën Eliza in Dukat to the bridge of Palasa.