Base course of first lot of Elbasan-Qafë Thanë road will be completed within this summer

Albanian Deputy Prime Minister, at the same time Minister of Infrastructure and Energy, Belinda Balluku inspected today the progress of works on the Elbasan – Qafë Thane road.
Balluku stated that within this summer, the entire base course of the road in lot 1 will be completed, while asphalting will begin in September.
According to Balluku, the inclusion of this road axis, part of Corridor 8, in the Pan-European corridor, also creates the possibility of financing the railway from EU funds.
“We have already the approval from the EU to include this segment, part of Corridor 8, in the Pan-European corridor. Only official approval is expected. The inclusion of this corridor in the Ten-T corridor makes Corridor 8 part of all European corridors, thus giving Albania the possibility for future funding for the railway from the EU and funds from banks that operate with EU funds,” Balluku was quoted as saying.
The Deputy Prime Minister added that this corridor will also serve the dry port of Struga in North Macedonia.
“This corridor has a very great value in terms of the new port of Durrës, as it foresees the direct connection with the new port of Durrës both through highways and the railway, thus supplying the dry port of Struga, which will to be part of the new port of Durrës, as we also have the dry port of Prishtina, which will of course will have access through The Nation Road,” said Balluku.
Balluku informed that within the month of June, the procedure for the second lot will be completed, which is also an important lot, starting from Miraka to Murrashi Bridge.
The head of the Albanian Road Authority, Evis Berberi, emphasized that the road exit of this segment in North Macedonia will not be the border point of Qafë Thana, but at another closer point, which will be connected by a 4-5 km tunnel. According to him, this change will shorten the distance to Struga by 20 km.
The Elbasan-Qafë Thanë road is of category B, with 2 lanes on each side, with lane dividers and all road parameters.
The works include not only the expansion of the existing road, but also the exit to a new axis of the road due to the increase in flow, while it also envisages improvement of the road parameters and the speed of movement.
/a.p./