Albanian Power Corporation (KESH) intends to buy fuel for the two floating thermal power plants in Vlora

The Albanian Power Corporation (KESH) has announced that in the frame of the development of the project for the temporary production of thermal power in the district of Vlora, it intends to provide the main combustible material for the production of energy.
In an announcement on its website, KESH recalls that the temporary thermal generating asset consists of two floating production assets with a total installed capacity of 110 MW.
Always according to KESH, the minimum quantity will be 100,000 (one hundred thousand) tons per year.
The floating TPPs arrived in Albania in 2022. The ships are located in the Triport of Vlora.
In a scenario for the energy situation during 2023, official data showed that the production of energy from these units would cost 165 million euros. The generators were expected to produce 884 GWh at a production cost of 185 euros/MWh.
/a.p./