Two new photovoltaic investments in Korça for electricity production

The Council of Ministers approved two new photovoltaic power plants in Korça County.

These projects are not concessions. Moreover, they do not receive state support.
Both plants must start operation within 36 months.

First, the company “TEKNO FIRE” Ltd will build a plant in Mbreshtan, Kolonjë Municipality.
The plant will have a capacity of 102 MW.
It will operate for 49 years.

In addition, the company must report every three months to the Ministry of Infrastructure and Energy and the National Agency of Natural Resources.
It must also respect environmental permits.
Furthermore, it must submit a contract guarantee.
Finally, it must provide 2% of annual production free of charge as a royalty.

Next, the company “KRONOS KONSTRUKSION” Ltd will build a second plant near Vërnik village, in Devoll Municipality.
This plant will have a capacity of 50 MW.
It will also operate for 49 years.

Similarly, the company must report regularly on construction progress.
It must respect environmental permits. It must provide a contract guarantee.
It must also deliver 2% of annual production to the Ministry.

Meanwhile, the Ministry and the National Agency will supervise both projects.
They will monitor construction, commissioning, and operation.
They will also verify quality and compliance.

Overall, these decisions aim to increase renewable energy capacity.
As a result, they strengthen the electricity sector.
They also support energy diversification and improve energy security.