Balluku at Vlora Airport Construction Site: Over 40% of Work Completed

Albanian Deputy Prime Minister and Minister of Infrastructure and Energy, Belinda Balluku, accompanied by the Director of Civil Aviation, Maksim Et’hemaj, visited the construction site of Vlora International Airport to see the project’s progress.

Rapid advancements are being made at the site, where the airport runway is under construction alongside the development of all associated airport infrastructure.

To date, over 40% of the physical work has been completed. Director Et’hemaj explained that the project is being developed in multiple phases, as initially planned.

“The airport is planned to be developed in three phases. This is the first phase, which will be followed by additional phases based on passenger numbers. The current progress involves a coordinated effort among various parties. The Civil Aviation Directorate, the airport, Customs, and the Police are working on defining requirements and determining staff allocations. The work is progressing very well,” said Et’hemaj.

The physical work is expected to be completed by the end of this year, after which the certification and validation processes for the airport, considered one of the largest in the region, will commence.

“The phases are clearly defined, specifying what will occur in each phase. A large civil aviation unit with multiple components cannot be built entirely in the first phase. According to the feasibility study, several phases are required to advance the construction process until the airport is fully operational. We are prepared according to a schedule and phased plan. For the first phase, which includes the initiation of operations and some sectors, we are fully ready,” stated Balluku.

The airport will develop in three sectors: civil aviation, aircraft maintenance, and a dedicated cargo sector, which Albania currently lacks. Minister Balluku emphasized the importance of adhering to deadlines, noting the country’s gained experience in finalizing such projects.

“We have excellent experts who are now familiar with the process. We successfully tested this with Kukës Airport, meeting deadlines and timelines. Our teams are experienced, have strong contacts with international partners, and have passed the significant test of Kukës certification. So, this is not a trial; it is a guaranteed success, provided we adhere to the deadlines,” emphasized Balluku.

Vlora International Airport will be a category 4E airport, with a 3.2-kilometer runway, enabling transoceanic flights.

/a.p./