The concrete lining of 22.2 km in the Murrizi Tunnel, part of the Arbër Road completed

Albanian Deputy Prime Minister, at the same time Minister of Infrastructure and Energy, Belinda Balluku, who was to see the works in the Murrizi Tunnel, part of the Arbër Road, says that while the work on the construction of all the road segments of the Arbër Road has been completed, there are still 400 meters to open to traffic, from the of 3.8 km of the Murrizi Tunnel.
Although the geological issues caused this tunnel not to be completed by the predetermined deadline, currently 2.2 km have been plastered with concrete lining in both entries of the 3.8 km tunnel.
The Director of the Albanian Road Authority (ARRSH), Evis Berberi adds that the work for the opening of the auxiliary tunnel of 3.78 km has also been completed. Currently, work is going on with the concrete lining, while 650 m has been completed so far.
According to him, in the first week of August, the road axes from the exit of the tunnel in Shkalla e Tujanit in the Murrizi Bypass up to the exit of the Maqellara Tunnel open to traffic.
/a.p./